考试题型是什么样的?
没改考纲版:目前考试题型是200道单选题,四选一,考试时长为4小时;
新考纲版:待确认
PMP考试题是双语的,中英文对照,英文在上,中文在下,所以不用担心语言问题。
考试样题:
While preparing the status report for stakeholders,the project manager discovers a negative
cost variance for a project where 10 percent of their work has been completed.What should the project manager do prior to meeting with the stakeholders?
A.Forecast the estimate at completion(EAC).
B.Initiate charge control procedures.
C.Put the project on hold until a response strategy is determined.
D.Use the contingency reserve.
1.在为相关方准备状态报告时,项目经理发现一成本偏差为负数,该项目 10%的工作己经完成,在与相关方开会之前,项目经理应该怎么做?
A.预测完工估算(EAC).
B.启动变更控制程序
C.搁置项目直到确定应对策略
D.使用应急储备